[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987672":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},987672,722,1,"单选题","关于网络图，下列说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","网络图的工具是箭条图",false,{"key":16,"text":17,"correct":14},"B","一项任务或工程，可以分解为许多作业，这些作业在生产工艺和生产组织上相互依赖、相互制约，网络图可以把各项作业之间的这种依赖和制约关系清晰地表示出来",{"key":19,"text":20,"correct":21},"C","网络图存在某些缺陷，它不能找出影响工程进度的关键和非关键因素",true,{"key":23,"text":24,"correct":14},"D","在日程计划与进度方面，人们常使用甘特图","通过网络图，能找出影响工程进度的关键和非关键因素，因而能进行统筹协调，合理地利用资源，提髙效率与经济效益。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]