[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},987669,722,1,"单选题","关键线路是由（ ）组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","非关键线路",false,{"key":16,"text":17,"correct":14},"B","非关键工序",{"key":19,"text":20,"correct":21},"C","关键工序",true,{"key":23,"text":24,"correct":14},"D","总作业量","关键工序就是在完成该工序的时间上，没有富裕时间，将关键工序连接起来，就是关键路线。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]