[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987668":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},987668,722,1,"单选题","网络图中的节点中，标出的两个时间是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最早完工时间和最迟完工时间",false,{"key":16,"text":17,"correct":18},"B","最早开工时间和最迟完工时间",true,{"key":20,"text":21,"correct":14},"C","最早开工时间和最迟开工时间",{"key":23,"text":24,"correct":14},"D","最迟开工时间和最迟完工时间","节点在网络图中，表示某一项作业的开始或结束，它不消耗资源，也不占用时间，只是时间的一个“交接点”。它所标出的两个时间是最早开工时间和最迟完工时间。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]