[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},987665,722,1,"单选题","( )只能给出比较粗略的计划简单的作业指示，表现不出作业间的从属关系。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直方图",false,{"key":16,"text":17,"correct":14},"B","网络图",{"key":19,"text":20,"correct":21},"C","甘特图",true,{"key":23,"text":24,"correct":14},"D","计划评审法","在日程计划与进度方面，人们常使用甘特图，但是甘特图只能给出比较粗略的计划简单的作业指示，由于表现不出作业间的从属关系，存在一系列的缺点。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]