[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},987664,722,1,"单选题","( )是把推进计划所必须的各项工作，按其时间顺序和从属关系，用网络形式表示的一种“矢线图”。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","排列图",false,{"key":16,"text":17,"correct":14},"B","树图",{"key":19,"text":20,"correct":14},"C","亲和图",{"key":22,"text":23,"correct":24},"D","网络图",true,"A项，排列图是为了对发生频次从最高到最低的项目进行排列而采用的简单图示技术；B项，树图就是把要实现的目的与需要采取的措施或手段，系统地展开，并绘制成图，以明确问题的重点，寻找最佳手段或措施；C项，亲和图是针对某一问题，充分收集各种经验、知识、创意和意见等语言、文字资料，通过亲和图进行汇总，并按其相互亲和性归纳整理这些资料，使问题明确起来，求得统一认识和协调工作，以利于问题解决的一种方法。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]