[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},987638,722,1,"单选题","排列图可用来确定采取措施的顺序，从排列图中（ ）的项目着手采取措施能够事半功倍。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","矩形柱面积",false,{"key":16,"text":17,"correct":14},"B","累计频数",{"key":19,"text":20,"correct":21},"C","矩形柱高",true,{"key":23,"text":24,"correct":14},"D","发生次数","排列图可用来确定采取措施的顺序。一般地，把发生率高的项目减低一半要比发生问题的项目完全消除更为容易。因此，从排列图中矩形柱高的项目着手采取措施能够事半功倍。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]