[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},987612,722,1,"单选题","某工程项目网络图如图所示，则（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工序E的最早开工时间为5",false,{"key":16,"text":17,"correct":18},"B","工序E的最早完工时间为5",true,{"key":20,"text":21,"correct":14},"C","工序E的总时差为8",{"key":23,"text":24,"correct":14},"D","关键线路为①-②-⑤-⑥","A项，节点2的最早开工时间tE(2) =0+3=3；BC两项，工序工序E的总时差为2，工序2的最早完工时间为3+2 =5；D项，在网络图中，关键路线是所有线路中耗时最长的线路。图中，线路①-③-⑥的时长为：2+7=9；线路①-③-⑤-⑥的时长为：2+6+6 = 14；线路①-②-③-⑥的时长为：3+5+7 = 15；线路①-②-③-⑤-⑥的时长为：3+5+6+6=20；线路①-②-③-⑤-⑥的时长为：3+4+6 = 13；线路①-②-④-⑤-⑥的时长为：3+2+3+6 =14；线路①-②-④-⑥的时长为：3 +2+5 =10；线路①-④-⑤-⑥的时长为：4+3 +6 = 13；线路①-④-⑥的时长为：4+5 =9。由此可知，关键线路为：①-②-③-⑤-⑥。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]