[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},987611,722,1,"单选题","网络图中的关键线路是指（ ）的线路。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","耗费时间最长",true,{"key":16,"text":17,"correct":18},"B","质量、可靠性影响最大",false,{"key":20,"text":21,"correct":18},"C","对最后完成工期影响最小",{"key":23,"text":24,"correct":18},"D","对成本或利润增减影响最大","关键线路是由关键工序组成。所谓关键工序，就是在完成该工序的时间上，没有富裕时间，将关键工序连接起来，就是关键路线。在网络图中，关键路线是所有线路中耗时最长的线路，关键线路上的时间之和是工程所需的时间，称为总工期。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]