[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},987610,722,1,"单选题","一项任务可以分解为许多作业，改进团队希望把各项作业进度间的依赖和制约关系清晰地表示出来，并通过适当的分析找出影响进度的关键路径，从而能进行统筹协调。此时适宜选择的工具是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","PDPC（过程决策程序图）",false,{"key":16,"text":17,"correct":18},"B","网络图（箭条图）",true,{"key":20,"text":21,"correct":14},"C","甘特图",{"key":23,"text":24,"correct":14},"D","亲和图","网络图是把推进计划所必须的各项工作，按其时间顺序和从属关系，用网络形式表示的一种“矢线图”。一项任务或工程，可以分解为许多作业，这些作业在生产工艺和生产组织上相互依赖、相互制约，网络图可以把各项作业之间的这种依赖和制约关系清晰地表示出来。通过网络图，能找出影响工程进度的关键和非关键因素，因而能进行统筹协调，合理地利用资源，提高效率与经济效益。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]