[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987582":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987582,722,2,"多选题","在确认计划是否有问题时，计划的问题往往是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","现状把握不准",true,{"key":16,"text":17,"correct":18},"B","对计划的传达或理解有误",false,{"key":20,"text":21,"correct":18},"C","没有经过必要的教育培训",{"key":23,"text":24,"correct":14},"D","对实施效果的测算有误",{"key":26,"text":27,"correct":14},"E","没有把握住实际拥有的能力","ADE","BC两项是确认是否按计划实施方面的问题。在确认计划是否有问题时，计划的问题除ADE三项外，还有计划阶段的信息有误和\u002F或知识不够，导致对策有误。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]