[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987565":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987565,722,2,"多选题","质量改进没有取得预期效果，可能的原因有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","没有按计划实施",true,{"key":16,"text":17,"correct":14},"B","计划编制错误",{"key":19,"text":20,"correct":21},"C","没有对计划实施过程进行合理监控",false,{"key":23,"text":24,"correct":21},"D","没有使用控制图",{"key":26,"text":27,"correct":21},"E","没有使用PDPC法","AB","没有达到预期效果时，应该从两大方面来考虑：①是否按计划实施了，实施方面的问题往往有：对改进的必要性认识不足；对计划的传达或理解有误；没有经过必要的教育培训；实施过程中的领导、组织、协调不够；资源不足；②计划是否有问题，计划的问题往往有：现状把握不准；计划阶段的信息有误和\u002F或知识不够，导致对策有误；对实施效果的测算有误；不了解实际拥有的能力。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]