[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987560":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},987560,722,1,"单选题","关于确认效果阶段，下列说法不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","用于改进前后比较的图表最好前后一致",false,{"key":16,"text":17,"correct":14},"B","将改进的成果换算成金额会让管理者认识到改进的重要性",{"key":19,"text":20,"correct":21},"C","只列出改进的主要效果即可，其他小的效果可不计入评价",true,{"key":23,"text":24,"correct":14},"D","采取对策后没有出现预期结果时，应从两个角度考虑原因","C项，确认效果时，如果有其他效果，不管大小都要列举出来。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]