[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987278":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987278,722,2,"多选题","在过程控制中要设置管理点，管理点的设置要遵循的原则有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设计所规定的关键质量特性和部位，特殊的质量特性及部位",true,{"key":16,"text":17,"correct":14},"B","特别要求的质量特性和项目",{"key":19,"text":20,"correct":14},"C","质量不稳定、事故多发部位",{"key":22,"text":23,"correct":14},"D","用户反馈意见多或经质量审核发现问题较多的项目",{"key":25,"text":26,"correct":27},"E","一般的质量特性及部位",false,"ABCD","管理点的设置必须依据过程的重要性及质量管理要求来确定，具体应遵循以下原则：①设计所规定的关键质量特性及部位；特殊的质量特性及部位；②特别要求的质量特性和项目；③质量不稳定、事故多发部位；④用户反馈意见多或经质量审核发现问题较多的项目。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]