[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987270":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},987270,722,1,"单选题","过程控制的实施是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","为保证产品质量而进行的质量检验活动",false,{"key":16,"text":17,"correct":18},"B","为实现产品生产过程质量而进行的有组织、有系统的过程管理活动",true,{"key":20,"text":21,"correct":14},"C","为了解产品的质量特性而进行的测试、测量活动",{"key":23,"text":24,"correct":14},"D","为控制产品质量而进行的统计分析活动","过程控制的实施是指为实现产品的符合性质量而进行的有组织、有系统的过程管理活动。过程控制的实施步骤包括对过程的识别、分析和控制。过程控制的前提是过程的识别。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]