[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987211":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},987211,722,2,"多选题","某轴承生产厂为了提高其产品质量，决定采用SPC。 控制图做好后，接下来需要考虑的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","控制图用于何处",true,{"key":16,"text":17,"correct":14},"B","如何选择控制对象",{"key":19,"text":20,"correct":14},"C","如何分析控制图",{"key":22,"text":23,"correct":24},"D","如何与其他控制图相连接",false,"ABC","应用控制图需考虑的问题包括：①控制图用于何处；②如何选择控制对象；③怎样选择控制图；④如何分析控制图；⑤对于点子出界或违反其他准则的处理；⑥控制图的重新制定；⑦控制图的保管问题。",{"id":6,"name":28,"category":29,"favorite":30},"中级质量专业理论与实务","建筑工程",0]