[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987168":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987168,722,2,"多选题","下列情形中，需要重新制定控制图的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","点子出界",false,{"key":16,"text":17,"correct":18},"B","环境改变",true,{"key":20,"text":21,"correct":18},"C","改变工艺参数或采用新工艺",{"key":23,"text":24,"correct":18},"D","人员和设备变动",{"key":26,"text":27,"correct":18},"E","更换原材料零部件或更换供应商","BCDE","控制图是根据稳态下的条件（即5M1E）制定的。如果条件变化，如操作人员更换或通过学习操作水平显著提高、设备更新、采用新型原材料或更换其他原材料、改变工艺参数或采用新工艺、环境改变等，这时控制图必须重新加以制定。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]