[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987163":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987163,722,2,"多选题","P控制图的控制对象是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","交货延迟率",true,{"key":16,"text":17,"correct":18},"B","不合格品数",false,{"key":20,"text":21,"correct":14},"C","缺勤率",{"key":23,"text":24,"correct":14},"D","差错率",{"key":26,"text":27,"correct":14},"E","不合格品率","ACDE","使用p图时应选择重要的检查项目作为判断不合格品的依据。p控制图用于控制对象为不合格品率或合格品率等计数质量指标的场合，包括不合格品率、交货延迟率、 缺勤率，差错率等。np控制图用于控制对象为不合格品数的场合。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]