[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987098":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},987098,722,1,"单选题","分析用控制图首先要分析过程是否处于稳态，（ ）的控制线延长能作为控制用的控制图。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","状态I，统计控制状态与技术控制状态同时达到稳态",true,{"key":16,"text":17,"correct":18},"B","状态II，统计控制状态未达到稳态，技术控制状态达到稳态",false,{"key":20,"text":21,"correct":18},"C","状态III，统计控制状态达到稳态，技术控制状态未达到稳态",{"key":23,"text":24,"correct":18},"D","状态IV，统计控制状态与技术控制状态均未达到稳态","状态IV是现场所不能容忍的，需要加以调整，使之逐步达到状态I。统计控制状态与技术控制状态同时达到稳态，是最理想的状态，在生产线的末道工序一般以保持状态I为宜。过程达到了所确定的状态后，才能将分析用控制图的控制线延长作为控制用控制图。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]