[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987073":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987073,722,2,"多选题","过程处于统计控制状态，则（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","过程中只有偶然因素，没有异常因素",true,{"key":16,"text":17,"correct":18},"B","过程中只有异常因素，没有偶然因素",false,{"key":20,"text":21,"correct":14},"C","过程能力指数未必满足要求",{"key":23,"text":24,"correct":14},"D","应继续判断过程是否达到技术控制状态",{"key":26,"text":27,"correct":18},"E","控制图中的点都集中在中心线附近的C区","ACD","统计控制状态，简称控制状态，是指过程中只有偶因而无异因产生的变异的状态。 过程能力指数的前提是稳态，σ表示过程离散程度，反映了产品加工质量；T是已确定的技术标准，不能由操作人员改变；σ越小，过程能力指数越大，当大到一定程度，经济上未必可行，所以并不是σ的值越小越好，过程能力指数未必满足要求，应继续判断过程是否达到技术控制状态。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]