[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},987057,722,1,"单选题","从SPC的角度看，一个合格的过程应当具备的条件是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","过程处于统计控制状态",false,{"key":16,"text":17,"correct":14},"B","具有足够的生产能力",{"key":19,"text":20,"correct":21},"C","过程处于统计控制状态并具有足够的过程能力",true,{"key":23,"text":24,"correct":14},"D","过程处于统计控制状态但过程能力不足","统计过程控制（Statistical Process Control，简称SPC）主要解决两个基本问题：一是过程运行状态是否稳定，二是过程能力是否充足。则一个合格的过程应当使过程处于统计控制状态并具有足够的过程能力。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]