[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-986270":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},986270,720,2,"多选题","进行最终检验的前提条件是（ ）。[2007年真题]",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","所有过程检验都已完成",true,{"key":16,"text":17,"correct":14},"B","所有进货检验都已完成",{"key":19,"text":20,"correct":21},"C","所有检验结果都得到顾客认定",false,{"key":23,"text":24,"correct":14},"D","之前的检验结果均满足规定耍求",{"key":26,"text":27,"correct":21},"E","所有检验方案都得到顾客认同","ABD","最终检验是产品质量控制的重点，也是产品放行交付（销售、使用）、使用的重要依据。最终检验应在所有规定的进货检验、过程检验都巳完成，其检验结果满足规定要求以后才能进行。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业相关知识","建筑工程",0]