[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-986214":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},986214,720,2,"多选题","在评价质量管理体系时，应对每一个被评价的过程提出若干基本问题，这些基本问题包 括（ ）。[2008年真题]",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","过程是否已被识别",true,{"key":16,"text":17,"correct":14},"B","职责是否已被分配",{"key":19,"text":20,"correct":21},"C","文件是否得到实施和保持",false,{"key":23,"text":24,"correct":14},"D","在实现所要求的结果方面，过程是否有效",{"key":26,"text":27,"correct":14},"E","过程是否被适当规定","ABDE","质量管理体系基于过程。在评价质量管理体系时，应对每一个被评价的过程，提出四个基本问题：①过程是否已被识别并适当规定；②职责是否已被分配；③程序是否得到实施和保持；④在实现所要求的结果方面上，过程是否有效。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业相关知识","建筑工程",0]