[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-986190":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},986190,720,2,"多选题","关于审核完成的有关内容，下列说法正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","当审核计划中的所有活动已完成，并分发了经过批准的审核报告时，审核即告结束",true,{"key":16,"text":17,"correct":14},"B","审核的相关文件应根据参与各方的协议，并按照适用的法律法规和合同要求予以保存或销毁",{"key":19,"text":20,"correct":14},"C","除非法律要求，审核组若没有得到审核委托方和受审核方的明确批准，不应向任何其他方泄露文件的内容以及审核中获得的其他信息或审核报告",{"key":22,"text":23,"correct":14},"D","如果需耍披露审核文件的内容，应尽快通知审核委托方和受审核方",{"key":25,"text":26,"correct":27},"E","审核文件可由审核组自主处理",false,"ABCD","审核的相关文件应根据参与各方的协议，并按照适用的法律法规和合同要求予以保存或销毁。除非法律要求，审核组若没有得到审核委托方和（适当时）受审核方的明确批准，不应向任何其他方泄露文件的内容以及审核中获得的其他信息或审核报告。如果需要披露审核文件的内容，应尽快通知审核委托方和受审核方。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业相关知识","建筑工程",0]