[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-986184":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},986184,720,2,"多选题","选择审核组时，保证帘核组整体能力的过程应包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","识别为达到审核目的所需的知识和技能",true,{"key":16,"text":17,"correct":14},"B","选择审核组成员以使审核组具备所有必要的知识和技能",{"key":19,"text":20,"correct":21},"C","对审核组成员进行必要的知识和技能培训",false,{"key":23,"text":24,"correct":21},"D","邀请相关专业的技术专家加人审核小组",{"key":26,"text":27,"correct":21},"E","审核小组内设专职监督人员","AB","在选择审核组时成考虑实现审核目的所需的能力。保证审核组整体能力的过程应包括：识别为达到审核目的所需的知识和技能；选择审核组成员以使审核组具备所有必要的知识和技能。若审核组中的审核员没有完全具备审核所需的知识和技能，可通过技术专家予以满足。技术专家应在审核员的指导下进行工作。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业相关知识","建筑工程",0]