[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-986183":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},986183,720,2,"多选题","质量管理体系认证比质量管理体系审核多出的活动有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","认证的申请与受理",true,{"key":16,"text":17,"correct":18},"B","文件评审",false,{"key":20,"text":21,"correct":14},"C","纠正措施的验证",{"key":23,"text":24,"correct":14},"D","监督审核与复评",{"key":26,"text":27,"correct":18},"E","现场审核的准备","ACD","典型的质最管理体系审核的主要活动包括：①审核的启动；②文件评审；③现场审核的准备；④现场审核的实施；⑤审核报告的编制、批准和分发；⑥审核的完成。而质量管理体系认证的主要活动包括：①认证申请与受理；②审核的启动；③文件评审； ④现场审核的准备；⑤现场审核的实施；⑥审核报告的编制、批准和分发；⑦纠正措施的验证；⑧颁发认证证书；⑨监督审核与复评。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业相关知识","建筑工程",0]