[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-986170":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},986170,720,2,"多选题","现场审核的主要活动包括（ ）。[2010年真题]",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","平行首次会议、末次会议",true,{"key":16,"text":17,"correct":14},"B","信息的收集和证实，并进行审核中的沟通",{"key":19,"text":20,"correct":14},"C","形成审核发现",{"key":22,"text":23,"correct":24},"D","采取纠正措施",false,{"key":26,"text":27,"correct":14},"E","准备审核结论","ABCE","现场审核的主要活动包括：①举行首次会议；②审核中的沟通；③信息的收集和证实；④形成审核发现；⑤准备审核结论；⑥举行末次会议。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业相关知识","建筑工程",0]