[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-986071":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},986071,720,2,"多选题","过程方法要求具体识别每一个过程。如对来料检验过程的识别应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对管理人员的识别",false,{"key":16,"text":17,"correct":18},"B","对待检的物料的识别",true,{"key":20,"text":21,"correct":18},"C","对测试结果的识别",{"key":23,"text":24,"correct":18},"D","对合格的检验员的识别",{"key":26,"text":27,"correct":18},"E","对结果判定所使用的依据文件的识别","BCDE","对每一个过程的识别包括输入、输出和活动的识别，也应包括活动所需资源的识别。来料检验过程的识别中，来料检验过程输入为一组待检的物料，输出应为测试结果，通常以书面报告形式给出，该过程的资源应包括：合格的检验员、检验活动所需的经校准的测量设备以及结果判定所使用的依据文件。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业相关知识","建筑工程",0]