[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},985943,720,1,"单选题","最终检验应在（ ）后进行。[2010年真题]",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","订货客户核实样品符合合同要求",false,{"key":16,"text":17,"correct":18},"B","规定的前期检验都已完成，其检验结果满足规定要求",true,{"key":20,"text":21,"correct":14},"C","规定的作业过程全部完成并签字确认",{"key":23,"text":24,"correct":14},"D","确认收到订货客户的预付款","最终检验是对产品形成过程最终作业（工艺）完成的成品是否符合规定质量要求所进行的检验，并为产品符合规定的质量特性要求提供证据。最终检验应在所有规定的进货检验、过程检验都已完成，其检验结果满足规定要求以后才能进行。",{"id":6,"name":27,"category":28,"favorite":29},"初级质量专业相关知识","建筑工程",0]