[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},985878,720,1,"单选题","质量管理体系认证的主要活动不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","认证申请与受理；审核的启动；文件评审",false,{"key":16,"text":17,"correct":14},"B","现场审核的准备；现场审核的实施；审核报告的编制、批准和分发",{"key":19,"text":20,"correct":14},"C","纠正措施的验证；颁发认证证书；监督审核与复评",{"key":22,"text":23,"correct":24},"D","审核的完成",true,"质量管理体系认证的主要活动内容包括：①认证申请与受理；②审核的启动； ③文件评审；④现场审核的准备；⑤现场审核的实施；⑥审核报告的编制、批准和分布；⑦纠正措施的验证；⑧颁发认证证书；⑨监督审核与复评。D项属于质量管理体系审核的主要活动内容。",{"id":6,"name":27,"category":28,"favorite":29},"初级质量专业相关知识","建筑工程",0]