[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},985852,720,1,"单选题","现场审核准备阶段的工作文件不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","检査表",false,{"key":16,"text":17,"correct":14},"B","审核抽样计划",{"key":19,"text":20,"correct":14},"C","支持性证据",{"key":22,"text":23,"correct":24},"D","审核准则",true,"现场审核开始前，审核组成员应评审与其所承担的审核工作有关的信息，并准备必要的工作文件，用于审核过程的参考和记录。这一阶段的工作文件包括：检查表和审核抽样计划；记录信息（例如：支持性证据，审核发现和会议记录）的表格。",{"id":6,"name":27,"category":28,"favorite":29},"初级质量专业相关知识","建筑工程",0]