[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},985850,720,1,"单选题","现场审核前，审核计划应经_ 评审和接受，并提交给 。（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","审核小组；审核委托方",false,{"key":16,"text":17,"correct":18},"B","审核委托方；受审核方",true,{"key":20,"text":21,"correct":14},"C","受审核方；审核委托方",{"key":23,"text":24,"correct":14},"D","审核委托方和受审核方；审核小组","审核组长应编制一份审核计划，为审核委托方、审核组和受审核方之间就审核的实施达成一致提供依据。在现场审核活动开始前，审核计划应经审核委托方评审和接受，并提交给受审核方。",{"id":6,"name":27,"category":28,"favorite":29},"初级质量专业相关知识","建筑工程",0]