[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},985553,718,1,"单选题","准时交货是顾客最关心的问题之一，为了监制准时交货率，宜采用（ ）。[2008年真题]",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","X－R控制图",false,{"key":16,"text":17,"correct":18},"B","p控制图",true,{"key":20,"text":21,"correct":14},"C","控制图",{"key":23,"text":24,"correct":14},"D","c控制图","P控制图用于控制对象为不合格品率或合格品率等计数值质量指标的场合，常用于控制不合格品率、交货延迟率、缺勤率、差错率等。",{"id":6,"name":27,"category":28,"favorite":29},"初级质量专业基础理论与实务","建筑工程",0]