[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985547":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},985547,718,2,"多选题","统计过程控制（SP C）是过程控制的一部分，主要内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","研究绘制控制图的原理与方法",false,{"key":16,"text":17,"correct":18},"B","利用控制图分析生产过程的稳定性，并对其变异进行预警",true,{"key":20,"text":21,"correct":14},"C","调查、统计历史资料，确定控制图的控制界限",{"key":23,"text":24,"correct":18},"D","计算过程能力指数，分析满足技术要求的程度，对过程质量进行评价",{"key":26,"text":27,"correct":14},"E","建立控制标准","BD","统计过程控制（Statistical Process Control，简称SPC)是过程控制的一部分，主要内容有两个方面：①利用控制图分析过程的稳定性，对过程存在的异常因素进行预警；②计算过程能力指数，分析稳定的过程能力满足技术要求的程度，对过程质量进行评价。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业基础理论与实务","建筑工程",0]