[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985537":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},985537,718,2,"多选题","作为分析用控制图，主要分析的内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分析生产过程是否处于统计控制状态",true,{"key":16,"text":17,"correct":14},"B","分析该过程的过程能力指数是否满足要求",{"key":19,"text":20,"correct":21},"C","分析有偏移情况的过程能力指数",false,{"key":23,"text":24,"correct":21},"D","计算过程的不合格品率",{"key":26,"text":27,"correct":21},"E","计算过程的偏移系数","AB","分析用控制图主要分析两个方面的内容：①所分析的过程是否处于统计控制状态；②该过程的过程能力指数Cp是否满足要求。维尔达把过程能力指数满足要求的状态称为技术稳态。",{"id":6,"name":31,"category":32,"favorite":33},"初级质量专业基础理论与实务","建筑工程",0]