[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985382":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},985382,718,1,"单选题","PDCA循环的内容分为四个阶段，下列各项属于C阶段的任务的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","根据顾客的要求和组织的方针，为提供结果建立必要的目标和过程",false,{"key":16,"text":17,"correct":14},"B","按策划阶段所制定的计划去执行",{"key":19,"text":20,"correct":21},"C","根据方针、目标和产品要求，对过程和产品进行监视和测量，并报告成果",true,{"key":23,"text":24,"correct":14},"D","把成功的经验加以肯定，形成标准；对于失败的教训，也要认真地总结","PDCA循环的内容分为P、D、C、A四个阶段。A项为P阶段的任务；B项为D 阶段的任务；D项为A阶段的任务。",{"id":6,"name":27,"category":28,"favorite":29},"初级质量专业基础理论与实务","建筑工程",0]