[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985054":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},985054,715,2,"多选题","以下关于建筑工程施工许可的表述中，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","因故不能在领取施工许可证后的3个月内开工时，可以申请延期",true,{"key":16,"text":17,"correct":18},"B","建设单位应当自领取施工许可证之日起两个月内开工",false,{"key":20,"text":21,"correct":14},"C","工程因故中止施工，建设单位应在中止施工之日起1个月内向原发证机关报告",{"key":23,"text":24,"correct":18},"D","中止施工满1年的工程恢复施工前，建设单位不必报发证机关核验施工许可证",{"key":26,"text":27,"correct":18},"E","对于符合条件的，发证机关应当自收到申请之日起20日内颁发施工许可证","AC","AB两项，建设单位应当在领取施工许可证后的3个月内开工。因故不能按期开工的，应当向原发证机关申请延期，延期以二次为限，每次不超过3个月。C项，在建的建筑工程因故中止施工，建设单位应当在中止施工之日起1个月内.向原发证机关报告。D项，建设工程恢复施工时，应当向原发证机关报告。中止施工1年以上的工程恢复施工前，建设单位应当报发证机关核验施工许可证。E项，建设行政主管部门应当在接到申请后的15日内，对符合条件的申请颁发施工许可证。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]