[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-985035":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},985035,715,2,"多选题","建设项目需要配套建设的环境保护设施，必须与主体工程同时()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","立项",false,{"key":16,"text":17,"correct":14},"B","审批",{"key":19,"text":20,"correct":21},"C","设计",true,{"key":23,"text":24,"correct":21},"D","施工",{"key":26,"text":27,"correct":21},"E","投产使用","CDE","建设项目的“三同时”制度，是指一切新建、改建和扩建的基本建设项目、技术改造项目、自然开发项目，以及可能对环境造成损害的工程建设项目，其建设项目需要配套建设的环境保护设施，必须与主体工程同时设计、同时施工、同时投产使用。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]