[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984962":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},984962,715,2,"多选题","我国目前对建设工程开工条件的审批形式有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","颁发施工许可证",true,{"key":16,"text":17,"correct":18},"B","颁发拆迁许可证",false,{"key":20,"text":21,"correct":14},"C","批准开工报告",{"key":23,"text":24,"correct":18},"D","批准竣工报告",{"key":26,"text":27,"correct":18},"E","颁发规划许可证","AC","开工报告制度是我国建设领域长期实施的一项制度。在我国目前的管理制度下，施工许可证与开工报告实际上是两种平行的制度，已批准开工报告的建筑工程不再领取施工许可证。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]