[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984914":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},984914,715,2,"多选题","关于分包工程的范围，下列说法错误的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建筑工程总承包单位可以将承包工程中的部分工程发包给具有相应资质条件的分包单位",false,{"key":16,"text":17,"correct":18},"B","承包单位可以将其承包的全部建筑工程转包给他人",true,{"key":20,"text":21,"correct":18},"C","施工总承包的，建筑工程主体结构的施工可以不由总承包单位自行完成",{"key":23,"text":24,"correct":14},"D","《招标投标法》规定，中标人不得向他人转让中标项目，也不得将中标项目肢解后分别向他人转让",{"key":26,"text":27,"correct":14},"E","分包工程发包人可以就分包合同的履行，要求分包工程承包人提供分包工程履约担保","BC","B项，《建筑法》第29条规定，禁止承包单位将其承包的全部建筑工程转包给他人，禁止承包单位将其承包的全部建筑工程肢解以后以分包的名义分别转包给他人；C项，施工总承包的，建筑工程主体结构的施工必须由总承包单位自行完成。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]