[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984799":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},984799,715,2,"多选题","关于工程项目招标采购交易成本，下列说法正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程项目招标过程中涉及招标人的交易成本主要包括事前成本、事中成本和事后成本",true,{"key":16,"text":17,"correct":14},"B","事前成本包括信息成本、技术成本、风险控制成本这三个方面",{"key":19,"text":20,"correct":21},"C","事中成本包括评标成本、政策成本和决策成本中三个方面",false,{"key":23,"text":24,"correct":21},"D","事后成本包括缔约成本、价格成本和招标直接成本三个方面",{"key":26,"text":27,"correct":14},"E","对招标人而言，影响工程项目招标交易成本的主要因素有项目的规模、项目的技术难度和招标机制的选择等因素","ABE","CD两项，工程项目招标过程中涉及招标人的交易成本主要包括事前成本、事中成本和事后成本，其中：①事前成本，包括信息成本、技术成本、风险控制成本；②事中成本，包括招标直接成本、评标成本、政策成本；③事后成本，包括缔约成本、价格成本、决策成本。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]