[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984783":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},984783,715,2,"多选题","下列关于成本分类方式的说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","根据成本与业务量之间的关系可划分为固定成本和变动成本",true,{"key":16,"text":17,"correct":18},"B","按成本发生与产品生产的关系可划分直接生产成本和间接生产成本",false,{"key":20,"text":21,"correct":14},"C","根据成本与产品生产工艺的关系可划分为直接生产成本和间接生产成本",{"key":23,"text":24,"correct":18},"D","根据成本与决策的关系可划分为边际成本、增量成本和差别成本",{"key":26,"text":27,"correct":14},"E","按计量单位可划分为单位成本和总成本","ACE","B项，按成本发生与产品生产的关系可划分为直接成本和间接成本；D项，根据成本与决策的关系可划分为相关成本与非相关成本。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]