[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984777":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},984777,715,2,"多选题","实际采购成本控制的具体方法有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对同类或类似项目合并分包招标",false,{"key":16,"text":17,"correct":14},"B","减少否决投标发生的概率",{"key":19,"text":20,"correct":21},"C","代理成本控制",true,{"key":23,"text":24,"correct":21},"D","控制资金利息成本",{"key":26,"text":27,"correct":21},"E","价格成本控制","CDE","中期成本控制一实际采购成本控制的具体方法有：①代理成本控制；②价格成本控制；③服务成本控制。A项属于缔约一招标操作成本控制；B项属于履约一验收及使用成本控制。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]