[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984774":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},984774,715,2,"多选题","招标采购的四大管理要素中，存在相互依赖和相互制约的关系的是招标项目()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","质量",true,{"key":16,"text":17,"correct":14},"B","成本",{"key":19,"text":20,"correct":21},"C","利润",false,{"key":23,"text":24,"correct":14},"D","时间",{"key":26,"text":27,"correct":21},"E","数量","ABD","招标采购有四大管理要素，即质量、成本、时间和数量。其中，招标项目质量、成本和时间进度三大目标之间具有相互依赖和相互制约的关系。某个管理要素的提高往往是以其他要素的降低为代价的。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]