[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984755":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},984755,715,2,"多选题","招标采购计划管理的主要任务包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","招标采购需求分析",true,{"key":16,"text":17,"correct":14},"B","确定采购主体",{"key":19,"text":20,"correct":14},"C","确定采购方式",{"key":22,"text":23,"correct":14},"D","招标采购策略",{"key":25,"text":26,"correct":27},"E","确定招标采购目标",false,"ABCD","招标采购计划管理的主要任务包括：①招标采购需求分析；②招标采购策略；③确定采购主体；④确定采购方式。E项属于招标采购计划管理的内容。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]