[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984737":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},984737,715,2,"多选题","一般而言，未能按时交付的原因包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","采购部门与用户部门关于交付时间有各自不同的理解",true,{"key":16,"text":17,"correct":14},"B","供应商出现了某些意外情况",{"key":19,"text":20,"correct":14},"C","紧急状况、意外状况的出现，让采购无法保证及时交付",{"key":22,"text":23,"correct":24},"D","采购的迟延交付",false,{"key":26,"text":27,"correct":14},"E","供应商在参与招标采购的过程中，为了中标而报出了其无法实现的交付日期","ABCE","按时交付是采购的重要目标。迟来的交付实际上意味着采购的失败，会减缓现金循环利用速度，并降低组织的效率或利润率。一般而言未能按时交付的情况往往是由以下原因造成的：①采购部门与用户部门关于交付时间有各自不同的理解；②供应商出现了某些意外情况，使其无法实现按时交付；③供应商在参与招标采购的过程中，为了中标而报出了其无法实现的交付日期；④紧急状况、意外状况的出现，让采购无法保证及时交付。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购专业知识与法律法规","建筑工程",1]