[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},984655,715,1,"单选题","根据《建筑法》规定，建筑工程主体结构的施工()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","经总监理工程师批准，可以由总承包单位分包给具有相应资质的其他施工单位",false,{"key":16,"text":17,"correct":14},"B","经建设单位批准，可以由总承包单位分包给具有相应资质的其他施工单位",{"key":19,"text":20,"correct":14},"C","可以由总承包单位分包给具有相应资质的其他施工单位",{"key":22,"text":23,"correct":24},"D","必须由总承包单位自行完成",true,"《建筑法》第29条规定，施工总承包的，建筑工程主体结构的施工必须由总承包单位自行完成。",{"id":6,"name":27,"category":28,"favorite":7},"招标采购专业知识与法律法规","建筑工程"]