[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},984648,715,1,"单选题","防治污染的设施不得擅自拆除或者闲置，确有必要拆除或者闲置的，必须征得所在地的()同意。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设行政主管部门",false,{"key":16,"text":17,"correct":14},"B","省级人民政府",{"key":19,"text":20,"correct":14},"C","县级以上人民政府",{"key":22,"text":23,"correct":24},"D","环境保护行政主管部门",true,"防治污染的设施必须经原审批环境影响报告书的环境保护行政主管部门验收合格后，该建设项目方可投入生产或者使用。防治污染的设施不得擅自拆除或者闲置，确有必要拆除或者闲置的，必须征得所在地的环境保护行政主管部门同意。",{"id":6,"name":27,"category":28,"favorite":7},"招标采购专业知识与法律法规","建筑工程"]