[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},984574,715,1,"单选题","建设单位应当自领取施工许可证之日起()个月内开工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","5",{"key":23,"text":24,"correct":14},"D","6","建设单位应当在领取施工许可证后的3个月内开工。因故不能按期开工的，应当向原发证机关申请延期，延期以二次为限，每次不超过3个月；既不开工又不申请延期或者超过延期时限的，施工许可证自行废止。",{"id":6,"name":27,"category":28,"favorite":7},"招标采购专业知识与法律法规","建筑工程"]