[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984413":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},984413,715,1,"单选题","建设单位取得施工许可证后，若不能按期开工，应当向发证机关申请延期，延期不超过()个月。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","",{"id":6,"name":27,"category":28,"favorite":7},"招标采购专业知识与法律法规","建筑工程"]