[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-984295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},984295,715,1,"单选题","某工程建设项目施工招标中，投标人递交了20万元投标保证金，在收到中标通知书后，又书面通知招标人放弃中标。现招标人有证据表明自己因中标人放弃中标而遭受30万元的损失。对于招标人来说，下列措施中最有利的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","没收中标人20万元投标保证金",false,{"key":16,"text":17,"correct":14},"B","没收中标人一半投标保证金",{"key":19,"text":20,"correct":14},"C","招标人不退还中标人的20万元投标保证金，并要求中标人再赔偿其30万元的损失",{"key":22,"text":23,"correct":24},"D","招标人不退还中标人的20万元投标保证金，并在此基础上要求中标人再赔偿10万元的损失",true,"中标人与招标人订立合同后，中标人或者招标人拒不履行合同，均构成违约，应当承担违约责任。中标通知书发出后，合同也已经成立，招标人改变中标结果的，或者中标人放弃中标项目的，也应当承担违约责任。缔约过失责任，是指在合同订立过程中，一方因违背其依据的诚实信用原则所产生的义务，而致另一方的信赖利益损失，并应承担损害赔偿责任。",{"id":6,"name":27,"category":28,"favorite":7},"招标采购专业知识与法律法规","建筑工程"]